The Seven Benefits That Will Change How You Evaluate Projects
Reliability isn't enough anymore—here are the 6 other criteria you must consider under FERC Order 1920
When American Electric Power's transmission planners began their first project evaluation under FERC Order 1920's new benefit criteria, they discovered that a $400 million transmission line they had rejected based purely on reliability metrics suddenly became economically justified when they included production cost savings, capacity benefits, and state policy support. The total quantified benefits exceeded costs by 2.3:1—transforming a "no-build" decision into a priority project.
This isn't an accounting trick or creative engineering economics. It's the fundamental shift that Order 1920 requires: moving from single-purpose reliability projects to multi-benefit infrastructure investments that must be evaluated across seven distinct value categories. For transmission planners and project development engineers, this represents the biggest change in project evaluation methodology since cost-benefit analysis was first introduced to the utility industry.
Yesterday we covered the foundational requirements of FERC Order 1920. Today, let's dive deep into each of the seven benefit categories, examine their engineering implications, and explore the calculation methods that are reshaping how we justify transmission investments.
The End of Reliability-Only Planning
Traditional Transmission Planning: For decades, transmission projects were justified primarily on reliability criteria:
N-1 Contingency: System performance during single equipment outages
Load Serving Capability: Ability to serve projected peak demand
Voltage Support: Maintaining acceptable voltage levels under contingencies
Economic Evaluation: Simple comparison of project costs vs. outage costs
Order 1920's Multi-Benefit Requirement: Every transmission project must now be evaluated across seven benefit categories:
Reliability Benefits
Adjusted Production Cost Benefits
Capacity Benefits
Decreased Transmission Losses
Increased Competition
Extreme Weather and Natural Disaster Recovery
State and Federal Policy Goals
This shift requires new analytical tools, expanded data collection, and fundamentally different approaches to project economics.
Benefit Category 1: Reliability Benefits
Traditional Approach:
Deterministic Analysis: Pass/fail criteria for N-1 contingencies
Planning Standards: Compliance with NERC reliability standards
Simple Metrics: Load at risk during contingency conditions
Order 1920 Enhancement:
Probabilistic Assessment: Risk-based reliability evaluation
Customer Impact Analysis: Economic consequences of outages by customer class
Cascading Analysis: Sequential failure scenario modeling
Climate Resilience: Enhanced reliability under extreme weather conditions
Engineering Implementation
Value of Lost Load (VOLL) Analysis:
Reliability Benefit = Σ (ΔLoad at Risk × VOLL × Outage Duration × Probability)
Customer Class Values:
Residential: $3-15/kWh depending on outage duration
Commercial: $15-50/kWh for most business types
Industrial: $50-500/kWh for process industries
Data Centers: $1,000-10,000/kWh for hyperscale facilities
Calculation Example: A transmission upgrade reduces load at risk by 500 MW with an annual outage probability of 0.1% and average duration of 4 hours:
Keep reading with a 7-day free trial
Subscribe to HIGH VOLTAGE AI NEWSLETTER to keep reading this post and get 7 days of free access to the full post archives.